6.2 Sequence Activities Process

The Sequence Activities process puts the activities in the order they need to be performed.

This process is not concerned with when the activities will occur on the project timeline, just in what order.

Properly sequencing activities involve determining the dependencies and relationships between activities and applying leads and lags.

Activity sequences are shown through project schedule network diagrams, which schematics are showing the order and relationships of project activities.

Sequence Activities process

Sequence Activities Process Decomposition

Sequence Activities Process: Inputs

  • Activity list
    The activity list is the complete list of project activities that are needed to produce the work packages.
    It's decomposed from the WBS work packages. It’s the source document this process needs to identify what the activities are that need sequenced.
  • Activity attributes
    The activity attributes document is a companion to the activity list.
    It provides sufficient detail to fully describe the activity, and any supplementary information about activity, such as its relationships, constraints, assumptions, dependencies, and responsible people.
  • Milestone list
    The milestone lists contain all project milestones regardless of where they originated and whether the milestone is optional or mandatory.
    Milestones can originate from the customer, performing organization, project manager, or project team.
    Milestones can generate dependencies and relationships between activities and might necessitate the need for leads and lags.
  • Project scope statement
    The product scope describes the characteristics and functionality of the product, service, or result.
    Compared to the project scope, it is more focused on explaining what the product will be and how it will be used.
    The scope statement may identify constraints that will generate dependencies and relationships between activities and might necessitate the need for leads and lags.
  • Organizational process assets
    Organizational process assets are the source of existing policies, processes, organizational data, and knowledge.
    These assets include the entire collection of formal and informal methodologies, policies, procedures, plans, and guidelines, as well as the organization's "knowledge base," which includes historical performance data. Of use to sequencing, activities could be data from prior projects.

Sequence Activities Process: Tools and Techniques

  • Precedence diagramming method (PDM)
    A method for producing project schedule network diagrams, PDM produces activity-on-node (AON) diagrams.
    These are schematics that show activity sequencing and relationships and are used in the Critical Path Methodology (CPM).
  • PDM includes four types of dependencies or logical relationships:
    • Finish-to-start (FS)​
      The initiation of the successor activity depends upon the completion of the predecessor activity.
    • Finish-to-finish (FF)​
      The completion of the successor activity depends upon the completion of the predecessor activity.
    • Start-to-start (SS)​
      The initiation of the successor activity depends upon the initiation of the predecessor activity.
    • Start-to-finish (SF)​
      The completion of the successor activity depends upon the initiation of the predecessor activity.

      In PDM, finish-to-start is the most commonly used type of precedence relationship. The start-to-finish relationship is rarely used but is included here for a complete list of the PDM relationship types.
  • Dependency determination
    When they exist, dependencies between activities can be mandatory, discretionary, or external.
    Mandatory dependencies are dictated by contract or the nature of the work; discretionary dependencies are a preferred sequence, and external dependencies are those controlled by factors outside the project.
  • Applying leads and lags
    Leads and lags are needed in the schedule for a variety of reason, such as dependencies between activities.
    Leads cause two activities to occur (for some period of time) in parallel when they'd normally have been sequential. Lags cause a delay between the finish of one activity and the start of the successor activity.
  • Schedule network template
    Templates can be helpful to decrease the time needed to create a project network diagram.

Sequence Activities Process: Outputs

  • Project schedule network diagram
    Project schedule network diagrams (PND) are schematics that show the sequencing of activities and activity interrelationships. The two types of diagrams are activity-on-arrow (AOA) and activity-on-node (AON).
  • Project document updates
    Sequencing of activities will usually result in updates to one or more other project documents.

Activity Dependencies

Dependencies restrict the order in which activities can be performed.

Dependencies should be described when they exist, usually on the activity attributes document as well as through narratives on the project schedule network diagram or through a supplementary document to the diagram.

There are three types of dependencies:

  1. Mandatory
    A required, hard logic, or inherent order to the activities. For example, a book can't be bound until it has been printed.
    Mandatory dependencies can also be caused by regulatory requirements or organizational procedures.
    Mandatory dependencies cannot be altered --they are what they are and the project has to adhere to those dependencies.
  2. Discretionary
    A logical or preferred order to the activities. For example, in a remodeling project, the team would prefer that carpeting not is installed until all painting has been completed.
    Discretionary dependencies can be reordered if necessary but doing so may result in additional risk factors.
  3. External
    The dependency is outside of the project and usually beyond its direct control. For example, a technician can't begin installing the equipment until the vendor delivers it.
    Though sometimes external dependencies can be influenced or made contractual (such as with a vendor or consultant), they can't usually be altered.
    External dependencies can also lead to scheduling problems when no hard data is available. For example, some modes of transportation can provide only a date range of when materials can be expected to arrive.

Activity Relationships

Activity relationships are another restriction that affects the order of activities by establishing the start and finish relationships between successor and predecessor activities.

Activity relationships

Activity relationships

If there is any unusual logic to the relationships, it should be documented in the activity attributes document as well as through narratives on the project schedule network diagram or on a supplementary document to the diagram.

There are four types of activity precedence relationships:

  1. Finish-to-Start (FS)
    The successor activity can begin only after the predecessor activity is completed (Activity B can't start until Activity A is completed). This is the most common type of relationship.
    For example, a house's concrete foundation can't be poured until the excavation activity is fully completed.
  2. Finish-to-Finish (FF)​
    The completion of the successor activity depends upon the completion of the predecessor activity (Activity B can't finish until Activity A is finished).
    This relationship is necessary when both activities need to finish at the same time (or very close) to each other, but there's not any relationship between the activity start dates.
    For example, in order to be ready for binding, the cover of a book needs to be completed around the same time as the printing of the book’s pages is done.
  3. Start-to-Start (SS)
    The successor activity can't start until the predecessor activity starts (Activity B can't start until Activity A has started). This relationship is needed when the starting dates of the activities are dependent upon each other, but the ending dates are not.
    For example, survey responses can start being tabulated as soon as the survey results begin coming in since there’s no real need to wait until all survey results have been returned before entering them into a database.
  4. Start-to-Finish (SF)
    The completion of the successor activity depends upon the predecessor activity starting (Activity B can't complete until Activity A has started).
    For example, in a project in which equipment is being replaced, before the old equipment can be fully decommissioned (Activity B), the initial testing of the new equipment should have been successfully started (Activity A).
    The testing doesn't need to be fully completed but just far enough along that the team can be assured the new equipment is functioning before the old equipment is dismantled.
Types of activity precedence relationships

Types of activity precedence relationships

Leads and Lags

Leads and lags are artificial effects on the timing of activities and are used in conjunction with activity relationships and dependencies.

Leads and Lags

Leads and Lags

Leads and lags and the reasoning behind their use should be well documented because it may not be obvious to the casual observer why they were established.

Lags are delays or waiting time between activities.

For example, if a parking lot is being resurfaced and there’s a 24-hour curing period for asphalt before striping can begin, there would be a one day lag between these activities used in conjunction with a finish-to-start relationship: Activity B (striping) can't begin until one day after Activity A (asphalting) is completed.

We can think of lag as positive time added to an activity's duration. If the asphalting task takes two days and there's a one day lag while waiting for it to cure, the duration of the asphalt activity is three days.

Leads speed up activities without changing the relationships between the activities.

We can think of leads as “negative” time because they allow activities to occur in parallel that would normally be done sequentially.

For example, after the parking lot has been resurfaced with asphalt and the painting of parking spaces begun, inserting the signs for handicapped spaces could start even though striping of the spaces isn’t done.

Activity C (posting handicapped parking spaces) will begin one day before Activity B (striping) is scheduled to be completed. Leads can lead to rework and usually pose other risk factors as well, so they should be used carefully.

Project Schedule Network Diagrams

Project schedule network diagrams, sometimes referred to by the acronym PND, graphically show the relationships, sequences, and durations of all activities from the start to the end of the project.

These diagrams are an integral part of the scheduling process and are necessary for determining the critical path of the project.

Most project management software applications will produce project schedule network diagrams, but we should know how to read them and create them by hand for the PMP examination.

Though time-consuming, producing them by hand, even if only at a summary level, has the added benefit of often uncovering missed activities, incorrectly sequenced, or erroneous relationships between activities.

There are two types of network diagrams:

The Arrow Diagramming Method (known as ADM) and the Precedence Diagramming Method (PDM).

For now, we're only concerned with properly sequencing the activities and don’t need to worry too much about the diagrams.

Later on during the Develop Schedule process (section 6.5), we'll spend more time with these diagrams as we add activity duration, calculate float, and use them to determine the project's critical path.

Arrow Diagramming Method (ADM)

The Arrow Diagramming Method (ADM) creates diagrams known as activity-on-arrow (AOA).

This is because ADM diagrams use activities shown on arrows and connected by nodes, usually shown as circles.

ADM is the oldest diagramming method and is now infrequently used. Its drawback is that it can only show finish-to-start (FS) relationships. In order to show relationships between tasks on different node branches, ADM diagrams use dummy activities.

These are fictional activities shown as dotted lines with duration of zero that join nodes.

In the example diagram, a dummy activity between E and C indicates that there's a finish-to-start relationship, activity C can't begin until activity E has been completed.

Precedence Diagramming Method (PDM)

The Precedence Diagramming Method (PDM) creates diagrams known as activity-on-node (AON). It uses nodes, usually shown as squares, to hold the activities which are connected by arrows to show the relationships.

The PDM diagram is the one most commonly used because it's more flexible and can show any activity relationship.

 

Leave a Reply

Your email address will not be published. Required fields are marked *

error: